Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the jetpack-boost domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/wp-includes/functions.php on line 6114
Development: 1 MW AC Springer Solar 1 Project | TurningPoint Energy

1 MW AC Springer Solar 1 Project

Springer Electric selected TPE in 2014 to help it fully develop, build, own and operate a 1 MW solar power plant.   After months of effort, TPE came to the conclusion that because Springer was a small rural cooperative, the most cost-effective means of ownership was inexpensive debt financing from its banks, avoiding the use of the federal solar investment tax credit.

  • No ITC & Low-Cost Debt Financing: Springer Electric financed the system through over $2.5 million in funding provided by USDA Rural Development’s Rural Utility Service (RUS).
CLIENT: Springer Electric Cooperative
LOCATION: Colfax County, NM
SYSTEM: 1 MW AC
COMPLETION: 2015
FINANCING: USDA Rural Utilities Service (RUS)

MW AC

Acres

Years of Clean, Renewable Solar Energy

Contact Us!
Send
Contact Us! Is your property suitable for solar?
Our team can quickly evaluate your site and market to see if the property is a fit to earn you extra money as a Community Solar Project host..
Send
Contact Us! Interested in becoming a Community Solar subscriber?
Contact us today to learn more about Community Solar subscription opportunities in your area.
Send
Send